Dear SAP Guru's,

in a process industry production takes place in different stages.

For a particular stage let us say Blending there will be 5 phases where we use different resources.

Instead of creating 5 resources in recipe i wish to go with one resource called blend.

At the same time i need to capture reporting data of resources of individual phases also.

How can this be achieved.

Should i go for secondary resources.

System by default will pick the resource assigned to operation for all the phases under it.

Kindly Give ur inputs

Thanks & Regards,

Karad D D

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Jul 12, 2009 at 06:04 AM

    pls reply to my this query

    Add comment
    10|10000 characters needed characters exceeded

  • Jul 12, 2009 at 11:15 PM

    for each operation in your routings you can set a "Control key".

    check it out.

    if you need to customize those keys goto tranz. OP00

    Add comment