cost center line items by profit center

Hi,

We have an issue, where user has processed a document in FI with profit center "X" however the cost center of the document has profit center "Y" in the master data.

In FI, accounting document showed against the profit center "X" with which user has processed.

In CO document profit center was coming with "Y whcih is in cost center master data.

There is a variance between FI and CO for profit centers.

However profit center account is not completly configured, it is configured minimally. So GLPCA, GLPCT do not fetch data for the given profit centers, I do not have profit center appearing in CO line item reports. We are using ECC 6.0 version.

Please help me to reconcile the difference.

Regards,

Ramesh.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Jul 15, 2009 at 03:53 AM

    HI

    In cost center onl;y cost get accumulated where as in profit center even balance shett items also get updated.

    so that might be the reason

    jain

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 15, 2009 at 04:17 AM

    Hi,

    I think your case for SAP is not normal process. Normally, if user assign separate profit center which is different to profit center in the Cost Object, lets say the cost center, during the posting the system will issue message that the profit center is changed the profit center assigned in the Cost object. System would not accept two different profit center on one posting process.

    For example:

    Posting material using assigment cost center X that contain profit center 1000, then also assign own profit center 1402.

    During posting, the system will issue message " the profit center is changed to 1000". This is what happen when there is discrepancy in profit center during posting.

    So, by having one profit center in a document, the data that flow from FI will follow the assignment in the Cost Object.

    For this problem, I think you need to raise this issue to OSS.

    Regards,

    Irhasni