KANBAN In Production still Generate Discrete Orders

marcoantonio_romerosanche
Active Participant
0 Kudos

Hello...

We are using KANBAN for In house Production, we define a new type of Order for this process.

We have the problem that the MRP is generating automatically the discrete production orders, and the KANBAN order do the technicall complete, so we have to reopen our KANBAN order and do technicall complete the production orders that MRP generate.

What we miss in configuration? how I can solve this issue?

Accepted Solutions (0)

Answers (4)

Answers (4)

marcoantonio_romerosanche
Active Participant
0 Kudos

A Production profile was created and also a new MRP controller for those special materials were created.

So the analyst will exclude them to run MRP.

marcoantonio_romerosanche
Active Participant
0 Kudos

Ratan, remmember, my material is KANBAN for Inhouse production,,, I need to plan it in order to transfer the requirement to the low level. It is a HALB material and needs to pass the requirement to the KAUF components.

marcoantonio_romerosanche
Active Participant
0 Kudos

We define in the PKMC the COntrol Type = 6 Working with production orders / MRP

Reduction POs = 3 All planned orders.

Planned Orders = NO Planned order creation

Former Member
0 Kudos

If you do not want the Material to be planned with MRP,maintain ND MRP type for that KAnban material.

Regards

Ratan

Former Member
0 Kudos

Hi,

Will you explain the problem detail?

In the control cycle select the strategy as production order with MRP.

So when you create kanban production order system will consume the MRP generated production order.

Regards,

Vijay