scheduling problem

dear Experts,

i am trying to schedule my project. in our projects we are using network, activities and activities are assigned to respective WBSE.

i want to enter the start and finish date of activity but when i create activity it automatically takes N/w start date as start date of activity and todays date as finish date of activity.

when i go in dates tab of activity to change the start and finish date it is disable for change. we can see the dates only. field is gray.

Please help me.

Regards

SONAL

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Jul 10, 2009 at 10:39 AM

    Hi,

    Now need of entering the start date and finish date for the activity. system it self define the start date and finish date of the activity by considering duartion entered.

    In network activity screen you have to enter the duration requires to complete activity in Normal Duration field.

    Maintain the Relation ship between the network activities and schedule the project.

    Regards,

    Nag.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 10, 2009 at 10:43 AM

    This message was moderated.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 10, 2009 at 10:48 AM

    Hi,

    goto OPU6 for the network type and plant combination check adjust dates in adjust scheduling is '3' or not i think it is '1'?

    even the field selection for netwok details as well

    Rgds

    Sudhir Reddy

    Edited by: sudhirreddy on Jul 10, 2009 12:49 PM

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi sudhir,

      thanks for your answer.

      i checked according to your instruction it is '3'.

      now what should i do?

      Regards

      Sonal