Dear all

i created one sales order for 1000 qty , and production order has been for 500 qty , now i want to block the sales order for the rest of the 500 qty line item 10

reply asap

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

5 Answers

  • avatar image
    Former Member
    Jul 10, 2009 at 08:27 AM

    Rahul,

    Your requirement is not clear, can you reexplain?

    Regards,

    Prasobh

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Eshwer,

      A locked production order still appears as a valid supply element. Therefore, MRP is in balance and new planned orders are not created. "Locking" only prevents the production order from being changed.

      TECO'd orders on the other hand, do NOT appear as supply elements. MRP assumes no further receipts will be forthcoming and would then create a new planned order.

      Rgds,

      DB49

  • avatar image
    Former Member
    Jul 10, 2009 at 07:37 AM

    in transcation code you can blok prod. order.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 10, 2009 at 07:41 AM

    hi,

    then what is the problem, you can do it.

    there is no check in standard sap for this.

    you can either change schedule line category to CN or you can go to reason for rejection tab of sales order and you can put reason for rejection for item 10.

    or you can change sales order say item no 10 and 20 and for 20 you can change schedule line to cn.

    that means it will not available for plan but if some one want to dispatch , user can dispatch it if stock exist.

    if you need further help please revert.

    Add comment
    10|10000 characters needed characters exceeded

  • Jul 10, 2009 at 08:46 AM

    Hi,

    As per my understanding the remaing qty 500 if you want to restrict instead of Make to Stock you can go for Make to Order Scenario.For this you ned to change your strategy for the particular materila in MRP 3 View.

    Hope it helps you i guess.

    Cheers,

    Kumar.S