Hello Everyone,
Process Orders after final confirmation appears in Detailed scheduling planning board, please suggest me where could I restrict process orders with status CNF to appear in planning board
Hello,
Please refer SAP consulting note 427264 - Acknowledged and fully delivered orders remain in APO
•Final confirmation on the manufacturing order in R/3
The order in APO copies the actual dates from R/3 and can still be displayed in APO.
Please read SAP note 492772 - Date transfer in confirmed operations not wanted
If you do not want a date transfer, you can ensure this using a user exit PPAPO007