Skip to Content
avatar image
Former Member

Total replenishment lead time

DearAll,

Are there any transaction codes to calculate the TRLT automatically? Since we create the routings for all HALB & FERT materials then system sholud suggest the TRLT. Please provide required information.

Regards,

SAP CONS

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    avatar image
    Former Member
    Jul 10, 2009 at 05:08 AM

    Hi,

    For in house produced materials, you might be interested to know that it is possible to update you material lot size independent processing time though:

    --> Go the routing of your material

    --> Go to the operations screen

    --> Select the menu Extras /Scheduling / Schedule

    --> Maintain the scheduling parameters you want in the pop-up that appears

    --> Select an overview variant (does not matter - you can change it when you want to test it again)

    --> towards the top of the screen there is a row of icons and option. There is one called Scheduling Result. Click that.

    --> In the pop of that window there is a button ' Update Material Master'. As the name indicates that will update your material master.

    Then go to transaction CA96 - Select the record created in the step above and update your material.

    Hope it helps.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 10, 2009 at 04:46 AM

    Hi

    no std report or t.code is there to show the TRLT. auto.

    if you need you can create the custom report for your reruirement with the material master and bom .

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 13, 2009 at 04:24 AM

    Since there is no reply I am closing the thread

    Add comment
    10|10000 characters needed characters exceeded