We want to schedule the back ground job for the cycle count for every week.i.e the Physical inventory document has to create accumulating that full week ,based on the indictor. But in MICN we have defaulting for one day date range. How to change the date period to one week ?

Thanks

JJ

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Jul 09, 2009 at 01:10 PM

    Create a variant by saving your selection.

    after clicking the save button, you are in the screen fro variant attributes.

    enter variant name and desciption

    Find the fields GIDAT and GBDAT.

    If you plan to run it e.g. every monday. then the monday will be your start date GIDAT and the next Sunday your to-date GBDAT.

    select GIDAT and find the column for selection variable, press F4 in that field and select D for dynamic selection.

    Then find field name of variable, press F4 and select current date.

    select GBDAT and find the column for selection variable, press F4 in that field and select D for dynamic selection.

    Then find field name of variable, press F4 and select current date +x days. then enter 7 in the pop-up.