During mrp run for a material (dependent req), the available qty is shown in negative.

0 Kudos

system not generating procurement proposals, even before that stock level for future periods are going extermely negative

Accepted Solutions (1)

Accepted Solutions (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

One possible cause for this issue is that you have a very long lead time for this product and you do not allow start in the past. In this case, MRP will use today as the start date for the new planned order and will run a forward scheduling to calculate the replenishment finish date. In this case, the finish date calculated may be in the future and you may have shortages within the lead time.

Another possible cause for this issue is a very long rescheduling horizon. In this case, a firm receipt in the future may be considered to cover those requirements and MRP will only trigger a rescheduling exception message. See this WIKI for details about rescheduling:

https://wiki.scn.sap.com/wiki/display/ERPMan/What+is+rescheduling+and+how+does+it+work

Regards,

Caetano

0 Kudos

Thank you Almeida,

We have tried changing all the attributes mentioned but still the issue persists.

Regards,

Ravi

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

I see a receipt of 74625 in week 49, which should clear all the shortages.

Do you see any exception message for this receipt element in MD05? What is the start date of this receipt?

Can you post a screenshot of transaction MD05 showing the MRP elements?

Regards,

Caetano

0 Kudos

Please refer attached

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

The mentioned replenishment element does not appear in your screenshot.

Regards,
Caetano

0 Kudos

please refer attached

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

There are many schedule lines with an end date on 05.12 and with a rescheduling message to the shortage dates.

As I mentioned earlier, whenever you have a long lead time and do not allow start in the past, you will have this kind of situation. If you check the planned delivery time in your material master, info record or scheduling you will probably find a long lead time here.

This is not an error at all, since your purchasing department cannot travel in time and start procurement for your material in the past 🙂

My suggestion for you is to teach your end users how to deal with this kind of situation and interpret the MRP exception messages.

Regards,

Caetano

Answers (3)

Answers (3)

Mahendran8888
Contributor
0 Kudos

As Almeida says this material can have high lead time. Agree with his points.

Mahendran8888
Contributor
0 Kudos

It is very clear that negative values are not negative stock or any stock, it is requirement,it is the dependent demand for superior product. Say for example you need 4 tyres for a car. SAP will communicate to you that Tyre -4. which means Car is required 4 tyres. When running MRP planned order will be created. Please ensure planned orders are available.

0 Kudos

mrp.pngadding Screenshot