Hi PM Experts,
Could you please check the below scenario and suggest the right solution?
Scenario:
I have created a multiple counter plan with the below details.
Cycle: 90 DAY/ 35000KM
Lead Float: 35 Days
Annual Estimate: 120,000 km
Start Date of the multiple counter plan: 02/09/2018
After Scheduling System proposed
Call Date: 16.12.2018 and Plan Date: 11.11.2018
Now, If I post crazy km reading (24000 KM) on 04.09.2018. IP30 proposes "New Save to Call" and creates Order with Basic Start Date as 02.09.2018(which is in the Past).
Is there any standard way to restrict Basic Start Date as Current Date?
If not which exit can be used here to control GSTRP(Basic Start Date) field?