Subcon PO

664 Views

Suppose I have to subcon a material X, where I need to provide 3 components: Y1, Y2, Y3 (defined in BOM) to the vendors.

When I created a subcon PO without account assignment, it works ok. I can see the components in ME2O. However,

When I created a subcon PO with account assignment 'E' (Cust. Indv. Reqt), I found that Y1, Y2 and Y3 in the components screen are marked with 'E'. When I run ME2O, nothing can be found. So, I can do the 541.

Actually, is it possible to have subcon PO with account assignment 'E'? Someone have experience in that?

Please advise. Thanks!

Ken