Hi,
We have Pos with multiple items and each item is assigned to different WBS elements. If any of the WBS elements assinged to those items has been set to statut TECO or CLSD, then we couldn't transfer the changes made to other items of the PO.
Every time system is validating the cost assignments for all the items. Even the item has been deleted, system is still validating the cost assignment details of the deleted item and gives an error.
Found the below SAP notes, but these are talking about service orders.
Note 878946 - One item TECO prevents other items from changing in ext. PO
Note 894688 - Unchanged item related status prevents others item's changes
We are in SRM 4.0. using extended classic scenario.
Could you please help me to fix this issue?
Thanks,
ss