Jul 07, 2009 at 10:35 AM

Progress analysis- Time proportionality

84 Views

Hi,

I am doing progress analysis by method- time proportionality for activity.

I have maintained a work package having the duration of 100 days ( for 5 months) . I have scheduled the project and run CNE1 and CNE5 and get the Planned POC as 22 % for the current period (4) fine. However if I am trying to run the progress analysis for next period (5), still I am getting the same planned POC as 22%. Why there is no change.

In my opinion the cumulative workdays should be 22+20 ( as per my calender) = 44, which is 44% of total days.

Also no copy of actual POC to activity on confirmation too.

Please advice where I am wrong

Regards

Zinni