Dear All,
I have this typical problem in budget supplement
Now suppose the top WBS budget is 300/-, and first level budget is 200/-
and against the budget of 200/- I have posted actual(assigned) values of 150/-
Now i want to change the first level WBS budget to 150/-
I tried to subtract 50/- from both first level and top level WBS
but got error, saying the budget is exhausted.
Availability Control is active for the Projects.
Regards,
Vikas Sharma