Hi,
I have Material A and Material B which are produced at same work center.
When I have requirement of A and B on suppose 15.07.2009,then when planned order are generated for these requirements date and time for prodcution dates are same for A and B.But practically it is not possible to process A and B at same time.
So I want the way through which system should consider already allocated order at workcenter.
e.p. During time 10.00 to 12.00,Planned/production order for A is already there then when I run MRP for B,Planned order for B should have start time as 12.00.Presently start time and end time for both are equals.
What setting I have to do to achive this?
Lalit Phegade