Hi All -
I have products A, B and C and I have lines 1 and 2. When I run product A on line 1 at a certain time, product B cannot run on line 2 for the next 24 hours. I should still be able to run C on line 2.
Appreciate if if you can give me some inputs on how to model this. I tried doing it through assigning line 2 as a secondary resource but it was not a good solution as line 2 would be blocked for all products and it will not let me run C either.
Thanks for your help