Jul 06, 2009 at 09:52 AM

Remaining work not showing correctly

84 Views

Hi,

For an internal activity i have maintained the data in the work field as 10 EA.on confirming i give the actual work as 3 EA and have not filled the forecast work and the degree of processing.when i run any report the values for remaining work is ZERO and the values for forecast work is shown the same as the actual work and the remaining work as ZERO.

where the error is occuring because as per my understanding the remaining work should be WORK-ACTUAL WORK= 7 EA in this case.

Thanks and Regards

Shekhar