Hi, Guys, I got a problem in Sales order ATP check .

Given pick/pack date = 5 days in shipping point, In-house production date = 1 day in material master, request delivery date in item = July06, no UU stock, It;s supposed to hv confirmed delivery date = July 14 (as material aval.date = July 07 ).

Somehow, system always propose delivery date = July 15.

If in-house date removed, the ATP gives right date as July 13 .(request delivery date = July 06, and pick/pack date = 5 days.) so, where's the one more day come from ? Pls share your comments...