Hi Experts,

We are getting error at the production posting stage that "existing std cost estimate cannot be utlised". This is because after the cost estimate there is some change in the routing or BOM.

Whether we have to do reorg of the material or rerun the std cost estimate. In which scenario we need to rerun the cost estimate and in which scenario we need to delete the existing std cost estimate and rerun the cost.

With regards

ACR.Ruben