Skip to Content
0
Former Member
Jul 03, 2009 at 11:11 AM

Error - Budget Return

225 Views

Dear Experts,

When I am trying to return the budget from a WBS element using T-Code CJ35, I am getting an error with Message No: BP164 "Capital investment budget exists for A-001 - update not allowed".

The WBS element A-001 is assigned to the Investment Program. Further It has two 2nd level WBS Elements which are assigned to it.

Budget returns can performed "Withing the Project" using CJ38. But not "From the project" using CJ35.

Very much appreciate your comments.

Thanks,

Dileepa.