Skip to Content
0
Former Member
Jul 03, 2009 at 08:00 AM

Redistributing overhead in COPA

314 Views

Hiya!

I am working with this client that has COPA implemented and after everything is settled and allocated in this module, they want to redistribute an ohverhead between the different products (Profit Centres) according to the COGS percentage assigned to each of their products.

Now, i looked in SAP and i couldn't find anything as such. I only found in PCA 3KE1/3KE5 but this this couldn't be moved into COPA as an adjustment, or at least i couldn't find the way.

The other way i found is by redistributing everything before settling (adjusting the overheads > confirmations) and then settling.

Could you please confirm that i am correct by suggesting this to the user? Is there any other way where you can create assessment within COPA to distribute the overheads by Profit Centre?

Many Thanks in advance.

fb.