Import from MS Project Client

Hello,

I have a requirement to implement the Import from MS Project Client.

The customizing is now implemented.

But the problem is if I import a MS Project Client file I have in cProjects a project definition which is ok. But then I have a "TASKHIERARCHY" as a phase and under this some tasks.

In MS Project I have a phase and some tasks under this phase.

How can i have a solution without this "TASKHIERARCHY"?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Jul 03, 2009 at 07:11 AM

    Hi

    did you check the note: 958210 in that refer to PPT file

    Rgds,

    I hope this helps

    Niranjan

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi

      No if you want to set the Activity in MSP as PHAsE you need to set text 20 it as Phase type and input the value there