Skip to Content
0
Former Member
Jul 02, 2009 at 06:13 PM

Billing on the basis of Progress

60 Views

Dear All,

My client requirement is Progress billing means after calculating progress by Work Method,system will calculate BCWP.

They cant bill on the basis of actual cost spend because some times actual work is not done but cost already spend.I am trying to ususe DP91 through Dip Profile to create a debit memo request ,it is working if i use source as actual cost-Line items but i am trying for Std indicatos but not working.

If somebody has worked on progress billing then please advice or any body can give some idea about this.

Muzamil