on 07-02-2009 11:42 AM
Hi Experts,
I have a created a shift planning profile and assigned to an org unit. Now I am running PP61 to plan the shifts. I had clicked on complete u201CTarget planu201D. Now I am not able to make changes in the shift plan through PP61. Please let me know how to edit completed target plan.
Thanks
Hi,
It´s not possible to edit a complete target plan, you have to "undo completed target plan" (PP6C), and after that you can edit it.
Best regards,
Marta.