Dear Experts,
Production order to be released at operation level automatically one by one, after confirmation of operation.
Let us suppose
Op 10 ...... 10 Confirmed
Op 20 ...... 10 Confirmed
then in the Op 30 ..... 4 Quantity to be released automatically once Operation 20 is confirmed and then after comfirming Operation 30, then operation must be released.
How to create trigger point for this?
Can anybody give clear idea, what all the fields I need to maintain ?
Oonemore thing, if I create a trigger point, how can I make it applicable to all orders with out manually changing every order in Change mode...