Dear All,

scenario is

In a plant if power is being produced and cement is also produced. if i declare power as a semifinished material and use repetitive manufacturing to produce that halb. and this halb is a part of BOM for cement(Fert) which is being procured by Process manufacturing (PP-PI). Is it ok or any problem with that.bcoz i m mixing repettitive and process manufacturing process.

what u suggest ,is it ok.

And one thing more can i use fert in the BOM of a fert.