Dear All,
We have a semifinished material for which SNP optimizer has generated SNP Planned orders for this component.
User has deleted SNP planned orders from Planning book,and execute PP Heuristic inorder to generate PP/DS planned orders.
PP/DS Horizon & SNP Horizon is defined as 'zero',the issue is why PP heuristic generating PP/DS Planned Orders up to 33 weeks.
I have checked PPDS Horizon is mainatined as 'zero' in Product master (/n/sapapo/mat1) & in version management.
My question is apart from this, Is there any other field from where 'PP/DS horizon' can be picked by PP heuristic.
Thhanks with regards,
Sajit