Skip to Content
0
Former Member
Jul 02, 2009 at 03:49 AM

PPDS Horizon is set 'Zero' ,Still PP heuristic is generating PP/DS Planned

120 Views

Dear All,

We have a semifinished material for which SNP optimizer has generated SNP Planned orders for this component.

User has deleted SNP planned orders from Planning book,and execute PP Heuristic inorder to generate PP/DS planned orders.

PP/DS Horizon & SNP Horizon is defined as 'zero',the issue is why PP heuristic generating PP/DS Planned Orders up to 33 weeks.

I have checked PPDS Horizon is mainatined as 'zero' in Product master (/n/sapapo/mat1) & in version management.

My question is apart from this, Is there any other field from where 'PP/DS horizon' can be picked by PP heuristic.

Thhanks with regards,

Sajit