PPDS Horizon is set 'Zero' ,Still PP heuristic is generating PP/DS Planned

Dear All,

We have a semifinished material for which SNP optimizer has generated SNP Planned orders for this component.

User has deleted SNP planned orders from Planning book,and execute PP Heuristic inorder to generate PP/DS planned orders.

PP/DS Horizon & SNP Horizon is defined as 'zero',the issue is why PP heuristic generating PP/DS Planned Orders up to 33 weeks.

I have checked PPDS Horizon is mainatined as 'zero' in Product master (/n/sapapo/mat1) & in version management.

My question is apart from this, Is there any other field from where 'PP/DS horizon' can be picked by PP heuristic.

Thhanks with regards,

Sajit

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Jul 02, 2009 at 07:23 AM

    Answer is no.

    Other then product master and version management no other place we can maintain the ppds Horizon.

    if you do not maintain any value any where then system will consider infinite PPDS Horizon.