Hi all
I have remove from the factory calendar one week becuse the procution is stopped, but when I run the MPS the system doesn't planned purchase requisition on this week.
Is there any way to differenciate both process, because althought the plant is not produccing, the deliveries have to be receipt and planned on these dates.
Thanks