Hi all,
Initially we create network xxx and activities 0010,0020,0030
Create PO AMT 44000 then do the GR /MIRO for 24000 amt My PO Still to be open for 20000 AMT
My requirement is that We change project structure YYY and activity 0050
How to transfer actual cosumed cost 24000 AMT from existing Network and activity to new assigned PROJECT/NETWORK ?
Vivek