Diffrence between working days & calander days

Former Member
0 Kudos

HI Gurus,

What is diffrence between working days and calander days.

In case of GR processing time in materail master it is working days but in case of planned delivery time it is calander days. Means planned delivery time is not consideruing any holidays, right.....

Regerds

ACP

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

GR processing time is time required o quality inspection and put material in store so it is specific to our plant. So it is consider in working days without any holidays.

Planned delivery time is the time required to vendor to provide the material delivery as so it is vendor specific. so it define in calender days including all holidays.

Please refer this link for more details,

[Planned Delivery Time|http://www.sap-img.com/materials/planned-delivery-time-as-workdays.htm]

Regards,

R.Brahmankar

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

Workings days ; will list the working days without the holidays.but

calender days ; consider also the leave days also.

so in GR processing time is used to the interal acitivities say that after receive the material GR the material need to do the GR process timing say inspection and documentations , then the material located to the Raw material sto location.

so the GR processing time is purelu based on the plant activies. so it consider the Working days only.

but in planned delivery time is given for vendor to delivary the material. so it consider the calender days .