Former Member
0 Kudos

Dear all

While doing GR, UOM problem occurs. The inspection plan UOM and Material UOM is not same i think. The material UOM is CAN.

Now the material is inwarded under movement 103. where in inspection plan, can i change the UOM? Kindly advice

Regards

Krupa (MM consultant)

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member186399
Active Contributor
0 Kudos

Dear Krupa

you can change the inspection plan UOM in the header. There you have the field " From Lot Size " in the General Data