PR created within network,the Plan/Actual/Budget Costs are stored in table COSS/COSP, right? How about PR created through TCODE ME51N?
Now we need to get the information:Project Definitions, Investment Programs, WBS Elements, Networks,Network Activities/Elements, Plan/Actual/Budget Costs, we can get this information from table RPSCO, COSS, COSP for PR created within network.If we want to get these information for PR created through TCODE ME51N, what should I do?
I have an existing program, customer says that the report only includes PR created within network, and want to add the PR created through TCODE ME51N, and I am new to PS, CO. Can anyone help me? Many thanks in advance!