Dear guru ,

I have a finished material that can be use both produced in-house and procured externally with subcontracting.

Now i use one only bom with usage 1 (production ) for the two process.

I have a problem for one component.

For subcontracting i must consider this component as a phantom (with explosion of its components) , instead for the in-house production I must consider this component as a normal stock item.

Can I use only one bom or I must create an alternative bom for manage the two cases ?