Hi all ,

While trying to create GR I am having the following problem.

Posting only possible in periods 2009/07 and 2009/06 in company code GRSM

Message no. M7053

Diagnosis

The posting date entered is not within one of the permitted posting periods (current period/previous period).

This can be due to one of two reasons:

The correct current period has not been set in the system.

For the system, the first of the entered periods is the current period. At the beginning of a new period, your systems administrator must change the current period in the material master record, using the function "Shift periods". This has not yet been done.

You have entered a wrong date in the field "Posting date".

Procedure

Check the posting date and correct it if necessary. If your input is correct, inform your systems administrator that the "period shifting" (period-end closing) process has not yet been completed. Copied from M8022"

I have checked the posting period.It was 03/2009.

So from MMPV I haved shifted it to 07/2009 with back posting allowed.

Now when I am creating a GR with posting period 01/07/2009 or 01/06/2009 I am having the above problem.

Please help.

Regards,

Anupam