Hi,
I have maintained strategy 10 in my finished product and components material master. I have created a manual production order of finished product.I have not maintained any BOM or routing. I have added components and operations in CO02.and saved the production order.
Now I run MRP in MD02.I got Purchase requisitions for the components.Now i added one more component in CO02 and saved the order. This time I selected , NETCH , adapt planning mode and removed the tick from 'also plan unchanged components ' from MD02 screen, expecting to get the Purchase requisition of the newly added component ( because any how Purchase requisition is already created for rest of the components in my last MRP run). But system did not create any purchase requisition for the newly created item.I put a tick in 'also plan unchanged components' and re run MRP. This time PRs got craeted.
Why didnt system create PR in my first scenario?? what is the use of tick and un tick of 'also plan unchanged components'
Can you all please explain???
Regards.