Inforecord Validity to be changed

Former Member
0 Kudos

Sir,

Ply help me out in changing te "Valid to" fileld which is in inforecord

Field Name "EINE-PRDAT"

Regards

Amey

Accepted Solutions (1)

Accepted Solutions (1)

0 Kudos

HI Amey,

After Clicking the conditions button,

A Pop up appears for Validity Periods:Conditions.

Click on New Validity Period,

Change the Validity Period

Enter Required Conditions

Save.

Regards.

Uday

Former Member
0 Kudos

PLY HELP ME IN CHANGING IN PURCHASE ORGANISATION 1 " DATA

REGARDS

AMEUY

Former Member
0 Kudos

Hi Amey ,

Inorder to change the validity to in Pur.Org Data 1 , u need to click on Conditions button.

Then change the valid t , save the changes .

This will automatically get updated in the Pur.Org Data screen.

Regards

Ramesh Ch

Former Member
0 Kudos

ply help

Answers (2)

Answers (2)

Former Member
0 Kudos

hI

gO TO mE12 - PURCHASING VIEW CLICK ON condition and then change the date

regards

Former Member
0 Kudos

Hi Amey ,

Click on Conditions button after entering into inforecord, then u will be able to change the Valid to field.

Regards

Ramesh Ch

Former Member
0 Kudos

we tried but it is not happening

Former Member
0 Kudos

Hi amey ,

What error did u get ?

Regards

Ramesh Ch

Former Member
0 Kudos

i am not able to change it is coming as grey

FYi

The Field is seen in Purchase Organisation 1 tab.

Regards

amey

Former Member
0 Kudos

Hi,

Validity to Period can not changed in Purchase org 1 data tab. It will come in Gray only.

Goto Condition tab there you can change the Valid to period or include the new validity Period.

rgds

gsc

Former Member
0 Kudos

Thanks so much.It really works.