Hi SAP Gurus
I have two differnt PO release strategy for 2 company codes.As we can use a single class for PO.whatever the characteristics defined for one relesae strategy ,the same are reflected for the other.
Now my problem is that for one release strategy i m using 'Cost centre' as a charateristics & it is notrequired for other.
But in relesae strategy whre 'Cost centre' is not required, i have to maintain the values in release stretgy & inwhile creating PO..Plesae tell me ,is there any option for that whre same class is in use.
please help me.
hi
At a time you can use only one class. If the cost center is one charecteristic for your first compay code and it is not required for the second one then in CL24n you cann asign all the cost centerfor the second one and selective cost center for the first one
Withthe help of cl24n you can solve it.
regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
One more option is their
Suppose your first company code is 1000
& 2nd one is 2000
Then create two strategies for two company code in first one you just assign 1000 and in second one 2000 and assign required cost center for first one and leave the field blank for the Ccode 2000
Hope this will help you
Edited by: Roy Anamika on Jun 29, 2009 12:30 PM
Ist company code 1000
and comany code 2000
for 1000
add cOMPANY CODE ALSO 1000Purchasing Doc type NB
Acct Assignment cat. D
purchasing group 101
Plant 9001
Total value & >0
Cost centre 100 ,200, 3000 ECT
fOR 2ND COMPANY CODE
cOMPANY CODE 2000Purchasing Doc type nb
Acct Assignment cat. d
purchasing group 101
Plant 9001
Total value & >0
Cost centre ---