Skip to Content
0
Former Member
Jun 28, 2009 at 11:49 AM

Deadline monitoring/Escalation - Purchase Requisition Workflow WS20000077

309 Views

Dear Friends,

I have read some stuff on SDN but still couldnt figure out the soultion.

Its a common problem. We have set a release strategy in Purchase Requisition and are using std workflow WS20000077.

Now the requirement is that if an approver doesnt approve in 2 days time then the PR will automatically go to the next approver for release.

I have set the deadline monitoring using the workflow wizard for model deadline monitoring. With this, The work item gets deleted from the approvers inbox. Next in the obsolete path I have set a process control which specifies the worklow step as the step in which deadline monitoring was specified.

When I check in SWI1, the work item is set as obsolete but it doesnt go to the next approver for approval.

Your replies will be highly apprecialted.

Thanks & Regards,

Fawaz