Former Member
Jun 27, 2009 at 08:51 PM

Purchase Reqs created in APO are not transfering to ECC6.0 automatically

45 Views

Hello all experts,

Recently we have upgraded our D01 and Q01 R/3 environments from ECC5.0

to ECC6.0. And now as part of testing the APO to ECC we are facing the

below mentioned problem.

Created few Purchase requisitions in the APO system after running

the heuristics in the SNP planning book but the data is not getting

transferred to the R/3 system automatically.

The Purchase Reqs are created immediately (which I can see by looking

at the distribution receipt details) but these P.Reqs show up in the

SCM Queue manager (/SAPAPO/CQ) only after 15 mins and we can see that

the P.Req are stuck in the queue with a status "Ready to be

transferrred" but never get converted to the actual R/3 P.Reqs.

On the R/3 side we can see these reqs in the inbound queue SMQ2.

We can manually force the APO P.Reqs to be pushed into R/3 either from

APO system using /SAPAPO/CQ transaction by selecting and clicking the

activate icon or from R/3 system using transaction SMQ2 by selecting

and clicking the activate icon.

Once we manually activate the APO P.Req then these go to R/3 and

convert to a actual P.Req and then this new number is immediately

updated on the APO side. No issues in this process. In the planning

book we can see the actual P.Req number from R/3.

Are we missing any connections? As part of upgrade do we need to do any settings on the R/3 or APO side? Your help would be greatly appreciated.

We have a golive coming up and are stuck with this issue.

Harry