Hi
I ran CCR on a location product for sales order.
System has give error 219 which says "Difference in material availability date (APO: 01.07.2009 13:00:00 <-> R/3: 24.06.2009 13:00:00)". So i tried "sent to APO". But not succesful, still the eror is there after iteration.
Now i had a acheck on sales order. The MAD is 01.07.2009.Why system has given error saying MAD in R3 is 24.06.2009.
Any body has experienced this problem. Please share.
Shall i delete in APO //SDORDER_DEL and again run CCR?
Please advice.
Thanks in advance
Vijaya.