Skip to Content
0
Former Member
Jun 26, 2009 at 09:21 AM

not consideration of production order during mrp run

248 Views

Dear Gurus

Is there any way so that the system will not consider the released production orders or partially delivered production orders which are there in the system without any requirement to be not considered for next planning run i.e the system should generate fresh planned orders for fresh requirements and will not consider the previously generated production order that has no requirement during the time of running mrp

Regards

Sandip Sarkar