Dear Forum,
This issue is with regards to the release strategy for Scheduling Agreement(SA)
Until now release has only been applicable to contracts at our client site. But we now plan to introduce it for SA as well. Such a feature is available in SAP but the problem is that with the given release strategy GR is not allowed until the release is affected. The system allows you to post the delivery schedule.
Now what I want is that after making the SA the system should not allow to make delivery schedule if release is not affected.
We also have MRP run at client site..Kindly suggest the procedure as, how to configure it.Are der any User Exit for the same,if so please discuss..
Warm Regards
Nainesh
SAP ECC 6.0