Former Member
Jun 25, 2009 at 06:26 AM

Scheduling problem in planned order.

31 Views

Hi all,

I have a problem in scheduling of planned orders.

I had mentioned the following parameters.

1. Available capacity in the work center as 06:00:00 to 12:00:00

2.Set up time is 10mins in the routing.

3. The planned order qty is 100 nos.

While doing manual scheduling in planned order, the system proposes the start time as 11:50am and finish time as 12:00am. But as per calculation, for 100nos x 10 mins = 1000 min = 17 hrs.

But the system calculated 10 mins for 100 nos.

Is there anything i am missing , due to which the system is doing wrong scheduling.

With regards,

Afzal