Hi Gurus,
Please help for the below mentioned data source(0TRAINING_ATTR) in BI production it is taking 19 hours to load the data of 28,000 records from ECC production.
u2022 The time taken only for bringing the records into PSA.
u2022 We didnu2019t enhanced the data source.
u2022 Settings for Parallel Processing
Number of Procesess : 3
Parallel Processing : Background (Job Class u2018Au2019)
u2022 In ECC form T-Code : SM50 I check and analysis the job for long time it is running some select * from HRP1001 where u2026u2026.. thousands of times.
Course (Attributes)
Technical name: 0TRAINING_ATTR
Delta update is not supported.
Type of DataSource :Attributes (Master Data)
Application Component :SAP Learning Solution (PE-LSO)
Regards,
Kiran Ankem
Edited by: Kiran A on Jun 27, 2009 11:20 AM