Dear Sirs,

While creating IM for work centers only (with selection criteria - work centers & plant), system checks and prompts a warning message that 'Capacity xxxxxxxx: Model does not contain plant'.

(Plant is ciffed to SCM system ahead)

What it's supposed to check and to fix it please?

Your kind advice is appreciated,

Thank you

Mandy

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Mandy,

Please check on the following:-

1) Check whether the work center/capacity/plant is assigned to model 000

2) Check whether the work center/capacity is maintained in ECC in all respects including capacity tab/scheduling tab

3) Check whether work center/capacity/plant has time zone maintained

4) Check whether capacity is maintained CR12 transaction in ECC and same is assinged while maintainng in CR02 transaction while maintaining work center

Regards

R. Senthil Mareeswaran.

Former Member
0 Kudos

Hi Senthil,

Thank you very much for the prompt attention!

For

2) Basic/Scheduling/Capacity data, its fine in ECC;

3) timezone is maintained in plant;

4) CR12 looks aligned with CR02.

Would please advice where to check if the work center/capacity/plant is assigned to model 000?

Thank you all the same,

Mandy

Former Member
0 Kudos

Hi Senthil,

Checking up the Location in Location Master Data with 'Assign Model' button, model 000 is ticked on the popup dialog box.

But one thing of concern: the Plant code xxxx is mapped in APO with the structure PLxxxx@XXXXXX, and the work centers are to be transferred by separate IM, does it matter to the issue?

Your further advice is appreciated,

Thank you

Mandy

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Mandy,

1) When you are transferring plant as XXX from ECC, it has to come and update with the same structure in APO in model 000

2) Check whether the plant is maintained within the work center before ciffing it.

3) Check in CFM5 transaction, whether active IM exists for plant

Please confirm

Regards

R. Senthil Mareeswaran.

Former Member
0 Kudos

Thank you very much for the info, Senthil!

Thru for 1) to 3).

By ignoring the warning message, the IM is activated and, work centers are transferred to SCM finally.

Much appreciated for the support,

Best regards,

Mandy