dear all
i have create one project having production wbs id. id-00034-03.
under this wbs id I create sub wbs id (id-00034-03-01,id-00034-03-02,id-00034-03-03)
w r t same material and quantity 1.
i have create wbs bom for all material with id-00034-03. for all the boms valid date is 01-06-2009. project schedule date is from 15-06-2009 to 30-07-2009.
when i run MRP wrt project ie MD51. system calculates only fg material and one assembly. actually bom is create as follows :
fg :
assly 1
assly 2
assly 3
each assembly contains 25 to 40 materials in its own bom.
but system only calculates fg material and first assembly only.
can anybody please explain where i am wrong ?