a new person responsible for WBS-element is needed.If I try to add Person respons. I get an error message. Entry xxxxxxx reponsible person does not exist in TCJ04 ---Check your entry..

Please tell me where i can do the entry....

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

First create the responsible person using OPS6 and use in your project.

Thanks

S.Murali

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Maintain Responsible person in OPS6 and then assign in CJ02..