Jun 23, 2009 at 08:52 AM

ECC forecast consumption (Planned Ind Requirements) in APO

257 Views

Good morning,

I have the following scenario:

I have Planned Ind. Requirements for 60 in ECC, this is being seen in APO.

I then create a planned order for 10 and I can see the reservation and open qty of the Planned Ind Req reduces to 50 (in both APO and ECC) this is as expected.

If I then issue (confirm the production and post 5 out of the 10 into stock). In ECC I now see I have 5 in stock, planned ord of 5 outstanding and the balance on the planned ind requirements of 50.

In APO I see stock of 5, planned order of 5 but the open qty of the planned ind requirement (checked in the forecast tab in the product view) has gone to 55 (so it is only looking at the planned orders (reservation).

I have checked the CIF and I get the following 3 documents going through to APO.

Stock update

Reservation Update

Planned Ind requirements (this document states there has been no change to the forecast).

I have come to the conclusion that we are not sending the forecast consumption info from ECC to APO,

How and were do there do this ??

Thanks in advance