ps quotation creation thru dp82 without inquiry?

115 Views

hi ps experts,

I am facing issue while creating quotation using dp82, as the quotation is not created with detailed network costings maintained in network -activities.

I am giving below the process i have followed and suggest/help what is to be done for getting detailed line itemwise quotation thru dp82

1. project created thru cj01 and wbs elements inserted & dip profile given in control area

2. network created thru cn21 and assigned wbs element

3. in network -ext. processing --> project materials ---

Material 1 - Rs.10000

Material 2 - Rs. 5000

Material 3 - Rs. 5000

4. dp82 is run with project defintion.

5. quotation is created as Material 1 - Rs.20000

my requirement is why i am not getting in quotation detailed as i have mentioned above in Network

Material 1 - Rs.10000

Material 2 - Rs. 5000

Material 3 - Rs. 5000

Pl help

Regards

srihari

ps: DIP configured used planned costs only.