hi ps experts,
I am facing issue while creating quotation using dp82, as the quotation is not created with detailed network costings maintained in network -activities.
I am giving below the process i have followed and suggest/help what is to be done for getting detailed line itemwise quotation thru dp82
1. project created thru cj01 and wbs elements inserted & dip profile given in control area
2. network created thru cn21 and assigned wbs element
3. in network -ext. processing --> project materials ---
Material 1 - Rs.10000
Material 2 - Rs. 5000
Material 3 - Rs. 5000
4. dp82 is run with project defintion.
5. quotation is created as Material 1 - Rs.20000
my requirement is why i am not getting in quotation detailed as i have mentioned above in Network
Material 1 - Rs.10000
Material 2 - Rs. 5000
Material 3 - Rs. 5000
Pl help
Regards
srihari
ps: DIP configured used planned costs only.